this update is brought to you by the Woodfield Country Club LRP committee
We continue to make progress in the Cascades building. The rough piping, electrical and ductwork have been completed. Drywall is currently being installed. Our current timeline goal (best-case but realistic scenario) is to have our second floor Fitness area open to members by September 29. The rest of the Cascades building is to open approximately November 5, as planned.
The opening date is dependent upon partial building opening approval by the City of Boca Raton, as well as normal construction variability.
Rest assured, overtime work is being done to try to improve the timetable so that you may enjoy the new facilities as soon as possible.
The pool complex (including the pools, new poolside restaurant, Kids Clubhouse and playgrounds) will open together late April 2016, as planned.
We are currently actively planning Phase 2 of the project (Clubhouse). This will be done in phases to maximize Clubhouse usability. Estimated overall construction is April - October 2016.
If you have any questions or interest in learning more about the renovations, both Phase 1 and Phase 2, at Woodfield, please feel free to contact me, Craig Greenberg 561-376-8540